Lynch Hill Academy, which started on site in January 2016, is a modular build construction comprising works both in Northern Ireland and Slough. With a significant percentage of the project being pre-fabricated off-site, “plug and play” methods were adopted to increase efficiency and maintain programme.
Harvey Group were responsible for the mechanical and electrical building services installation, which compromise, energy efficient LED lighting complete with daylight dimming PIR's, CCTV, Data, power and infrastructure and disable facilities.
Underfloor heating was installed within the Sports Hall, with VRF heating/cooling utilised within the classrooms and LTHW Radiant panel installation in communal areas. Specialist Lab Gases were installed throughout Science Laboratories.
This Quality project was successfully completed early 2017 and was handed over, on time and within budget.
(Image Credit: McAvoy Group)