At 250,000 square feet City Quays 3 is one of the largest Grade A office developments to be built in Northern Ireland. It is the third phase of the 10-hectare City Quays development in Belfast Harbour and Harvey Group are proud to say the 3rd project completed for Belfast Harbour Commission in the City Quays scheme.

Harvey Group PLC were appointed as the mechanical & electrical contractor to design, develop & install the MEP building services.

MEP Services included:

  • Chilled water installations
  • Sprinkler
  • LTHW heating systems
  • Domestic hot & cold water systems
  • Ventilation via air handling units
  • Gas installation
  • Above ground drainage
  • HV & LV distribution
  • Small power & data
  • CHP
  • Primary & Secondary Containment
  • General lighting, emergency lighting & controls
  • Fire alarm, PAVA & disabled refuge
  • Security systems including intruder alarm, access control & CCTV

 

This project was delayed due to COVID-19 and Harvey Group designed prefabrication solutions which were utilised extensively to mitigate the effects of the pandemic on programme. Following prefabrication at our workshop in Newtownabbey, we successfully installed the chilled water pipe frames into risers & chilled water heat exchanger skids into the basement and risers (for more information on pre-fabrication please “click here”.)

Image Credits: WH Stephens & Farrans 

Main Contractor

Farrans Construction
99 Kingsway
Dunmurray
Belfast
BT17 9NU

M&E Consultants

Tetra Tech
Locksley Business Park
1 Montgomery Road
Belfast
BT6 9UP

Architects

RPP Architects Ltd
155-157 Donegall Pass
Belfast
BT7 1DT