Castlecourt Offices

The redevelopment of the Castlecourt Offices provides modern open plan office accommodation over the second, third and fifth floors. During the initial 12 week design development phase prior to construction, we worked closely with main contractors, O'Hare McGovern and M&E Consultants, Beattie Flanigan, developing the Mechanical and Electrical design to installation stage.

The works were carried out over 4 phases:

  • Phase 1 - 5th Floor
  • Phase 2 - 3rd Floor
  • Phase 3 - 2nd Floor
  • Phase 3A - 2nd Floor

Demolitions of Mechanical and Electrical installations included circuits, data cabling, cover plates, spine trunking, ventilation ducting, radiators and associated pipe-work. Some of our works included removal of oil fired boilers which were replaced with new gas fired boilers and associated flues.

A new Gas Fired VRF and fresh air system was installed with complete new BEMS system with integration to existing. A new Public Address system, Information Technology facilities, Small Power installation, Lighting and Fire Alarm systems all formed part of our works.

Key Features are:

  • Very Good BREEAM
  • Live Site
  • NEC3 Option C Contract

Main Contractor

O'Hare McGovern
Carnbane House
Shepherds Way
Carnbane Industrial Estate
Newry
BT35 6EE

M&E Consultant

Beattie Flanigan
40 Montgomery Road
Belfast
BT6 9HL

Architects

Isherwood & Ellis Architects
1 Lower Crescent
Belfast
BT7 1NR